Junior Warden, Annual Report, 2011
Elizabeth Heimbach
I. Major projects
1. Crack under the gallery on the driveway side repaired
2. Damaged sacristy chimney removed
3. Vertical crack beside the sacristy door filled
B. Repair of the duct work under the nave and replacement of the old furnace and air conditioner completed by Harrie Plumbing and Heating; old oil tank and furnace given to Habitat for Humanity
C. Repairs to the organ completed by Mark Thompson (one pipe still needed)
D. Work in progress by Shenandoah Glass on the stained glass in the gallery
II. Smaller projects
B. Graveyard fence completed by the Pitts Brothers
C. Rectory porch and ramp and church ramp painted by the Andersons
D. Rectory back door frame replaced by Rick Chenault
E. Rectory outside wall on the cottage side repainted by Rick Chenault
F. Cottage roof repainted by Rick Chenault
G. Plaque marking the belfry project donated by David Storke and installed on the outside wall of the church on the graveyard side; framed parchment with list of donors
H. Replacement of the sacristy water heater completed by Clarence Kunstmann
I. Replacement of the rectory dishwasher with new dishwasher donated by Vivian MacDonald and Steve Price
III. Future projects
A. Repair of the leaking window in the upstairs Sunday school room of the rectory
B. Paint for the ceiling over rectory stairs
C. Repair of the electrical outlet by the piano in the nave of the church
D. Paint for the rust spots in the stucco of the church walls
E. Discussion of a maintenance agreement with Bob Harrie